Ontario Excess Soil Rules for Homeowners and Small Projects

48 minutes ago
6 min read

For most homeowners, Ontario's excess soil regulation (O. Reg. 406/19) doesn't require registry filings or formal soil management plans. Those planning rules apply mainly to projects producing 2,000 m³ or more of excess soil in settlement areas, and they exclude most residential and agricultural properties. But the regulation's basic rules still apply to every load: soil must go somewhere it serves a real purpose, sites can't take more than they need, and haulers keep records for loads of 5 m³ or more. Hiring a contractor who knows where your soil is going protects you from illegal dumping problems.


Pool removals, foundation digs, drainage trenches and landscaping projects all create piles of extra soil. This guide explains what Ontario's excess soil rules mean for homeowners and small builders in London and southwestern Ontario, which exemptions usually apply and what to ask your contractor.


What Is "Excess Soil"?


Excess soil is soil, or soil mixed with rock, that is dug up during a project and has to leave the site because it can't be reused there. Ontario regulates it under O. Reg. 406/19, On-Site and Excess Soil Management, made under the Environmental Protection Act.


The goals are to:


  • Keep clean soil out of landfills where it can be reused

  • Stop illegal dumping of soil on farms, woodlots and vacant land

  • Make sure soil goes to a site where it is appropriate and needed


Key Dates


Date

What changed

January 1, 2021

Reuse rules took effect

January 1, 2023

Testing, tracking and registry rules took effect

October 2025

Amendments (O. Reg. 235/25) eased rules mainly for infrastructure and aggregate projects

January 1, 2027

Ban on sending reusable, cleaner soil to landfill takes effect (delayed from 2025)


Do the Planning Rules Apply to My Project?


The heavier planning requirements, including filing a notice in the Excess Soil Registry, preparing an assessment of past uses, sampling and analysis, and tracking each load, apply to projects that produce 2,000 m³ or more of excess soil inside a settlement area.


They generally don't apply where:


  • The project is in a rural area outside a settlement area

  • The whole project area is, or was most recently, used for residential, agricultural, parkland or institutional use, as defined in Ontario's brownfields rules


They do apply, whatever the size, to "enhanced investigation project areas", such as former gas stations, garages, dry cleaners and industrial sites, and to soil remediation projects.


For a typical home project in London, such as a pool removal, a basement dig or a backyard regrade, the registry and planning rules usually won't apply. Still, check with your contractor if the property has any history of commercial or industrial use.


Other exemptions from reuse planning


Ontario's fact sheet lists more exemptions, including:


  • 100 m³ or less taken directly to a landfill or disposal site

  • 100 m³ or less taken to a local waste transfer facility

  • Topsoil moved directly for reuse as topsoil, where contamination risk is low

  • Emergencies

  • Routine infrastructure maintenance, other than stormwater pond clean-out


Yellow and black heavy equipment working on brown soil

Rules That Apply to Every Load


Even when a project is exempt from planning, the regulation's general rules still matter.


Where soil goes


Soil can only go to a reuse site where it serves a beneficial purpose, such as grading, backfilling or landscaping, and the site has the permissions it needs. Ontario's guidance says:


  • Dumping or stockpiling soil with no purpose doesn't count as reuse.

  • A site can't bring in more soil than its project needs.

  • Only dry soil is allowed, unless a site has a specific approval for liquid soil.

  • Soil can be stored at a reuse site for up to 2 years. A Director can extend that.


Large reuse sites receiving more than 10,000 m³ must file in the registry and track loads. All residential development soil depots must file.


Hauling records


Haulers moving excess soil must carry hauling records, except for loads under 5 m³. Records are kept for 2 years. Reuse sites keep their records for 7 years.


Soil quality


Soil must meet quality standards for where it's going. Ontario uses different standards tables depending on the volume and the receiving site. For example, smaller "volume-dependent" tables apply to loads up to 350 m³, and the strictest background standards apply to sensitive land like cropland and pasture.


What This Means for Common Projects


Pool removal


A pool removal often brings soil in rather than taking it out. Backfill and topsoil are imported to fill the hole. Your contractor should know where the fill comes from and what's in it. If concrete and debris are hauled away, they should go to a proper facility. See our pool removal procedure and Compacting a Filled-In Pool.


Basement, addition and foundation digs


These create the most excess soil on a home project. Some can go back as backfill. The rest has to leave. Ask where it's going.


Landscaping and regrading


Most landscaping moves small volumes. Good topsoil can often be reused on-site. Our article on fill dirt vs. topsoil explains which material belongs where.


Bringing fill onto your property


If someone offers you "free fill", be careful. Under the regulation, a site shouldn't take more soil than it needs, and soil quality must suit the land. You may also need municipal or conservation authority approval to place fill. In London, regrading or placing fill near a creek, valley or wetland may need a UTRCA permit under O. Reg. 41/24. Many municipalities also have site alteration or fill by-laws.


Questions to Ask Your Contractor


  1. How much soil will leave the site? Get an estimate in cubic metres or yards.

  2. Where will it go? Ask for the destination: a reuse site, a licensed facility or a landfill.

  3. Does my project trigger the registry or planning rules? Usually not for residential lots, but ask.

  4. Will hauling records be kept? Required for loads of 5 m³ or more.

  5. Where does the imported fill come from? Especially for pool fills and grading.

  6. Do we need a municipal or conservation authority permit? For grading, fill or work near water.

  7. Who requested the utility locates? Ontario One Call is required before any digging. See our excavation checklist.


Why It Matters to Homeowners


Even if most of the regulation is aimed at large projects, homeowners can still end up dealing with problems:


  • Illegal dumping can be traced back to the source project.

  • Accepting unknown fill can leave contaminated or unsuitable material on your property, which can affect drainage, plants and resale.

  • Cheap disposal quotes sometimes mean soil goes somewhere it shouldn't.


A reputable contractor builds legal hauling and disposal into the price.


FAQ


Does O. Reg. 406/19 apply to my home renovation?


The planning and registry rules usually don't. They apply mainly to projects producing 2,000 m³ or more of excess soil in settlement areas, and they exclude most residential and agricultural properties. General rules about where soil can go and hauling records still apply.


Do I need to register my project in Ontario's Excess Soil Registry?


Most homeowners don't. Registry filings are generally needed for larger projects in settlement areas, enhanced investigation sites such as former gas stations or industrial land, large reuse sites and residential development soil depots.


What is the minimum load that needs a hauling record?


Haulers don't need hauling records for loads under 5 m³. Loads of 5 m³ or more need records, which haulers keep for 2 years.


Can I accept free fill on my property in Ontario?


Be careful. The regulation says a site shouldn't receive more soil than it needs for a beneficial purpose, and soil quality must suit the land. You may also need a municipal site alteration permit or a conservation authority permit. Ask where the fill came from.


When does Ontario's ban on landfilling clean soil start?


January 1, 2027. It was delayed from January 1, 2025.


Excavation and Hauling Done Right


SPM Landscape & Excavation handles excavation, grading, pool removal and material delivery across London and southwestern Ontario. We've operated since 2006, we're WSIB covered and we carry $1M liability insurance. Call (519) 474-0008 or email spmlandscape@gmail.com for a free quote. Need topsoil or fill? See our topsoil products.



This article is general information about Ontario's excess soil rules, not legal advice. Check the regulation or speak with a qualified person for your project.